SrNo | WORK ORDER NO | CIRCLE | WORK NAME | ESTIMATE COST & DATE | TENDER AMOUNT & DATE | AGREEMENT DATE & ACTUAL WORK START DATE | Target date of Work Completion | Agreement date & ACTUAL work start DATE1 | CONTRACTOR NAME & PHONE NO. | ENG. NAME AND PHONE NO | circle1 | Physical Progress |
1
| D/55/AEM/16-17 | Circle 1 | Commercial Complex And Hotel Block Bus Stand at vikas nagar u.p.s.r.t.c compound Kanpur Nagar. | 0.00 | 12641.62 10/06/2016 | 27/07/2016 01/08/2016 | 31/08/2018 | 27/07/2016 01/08/2016 | RAMKEE INFRASTRUCTURE LTD. 9999999999 | C.B. PANDEY 7060505014 JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134 EX | Circle 1 | In Progress |
2
| KDA/Z4/3 | Circle 1 | | 0.00 | 644.79 | 13/12/2013 | 31/12/2018 | 13/12/2013 | | Ram Avatar7706909305 JE MOHAMMAD QUAMAR 7706909313 AE RANA PRATAP SINGH 7705917134 EX | Circle 1 | In Progress |
3
| D/291/AA-1/18-19 | Circle 1 | Consraction Of RCC Road Police Line Compound Kanpur Nagar. | 0.00 | 94.39 23/10/2018 | 29/12/2018 31/12/2018 | 30/03/2019 | 29/12/2018 31/12/2018 | Devi Enterprises 9839350217 | HASAN RAJA 9415087398JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134XE | Circle 1 | In Progress |
4
| D/298/AA-1/18-19 | Circle 1 | Beautification Work Near Sarsaiya Ghat situted the Ganaga River Bank Kanpur. | 0.00 | 89.87 27/11/2018 | 07/01/2019 08/01/2019 | 07/06/2019 | 07/01/2019 08/01/2019 | Atal Gopal Builders 9452486562 | C.B. PANDEY 7060505014JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134XE | Circle 1 | In Progress |
5
| D/312/AA-1/18-19 | Circle 1 | Construction Of Culvertes on nala at Bairi Akacarpur from Amit gas Agency to mankadikheda Bithoor Road kanpur. | 0.00 | 23.63 17/11/2018 | 22/01/2019 | 21/04/2019 | 22/01/2019 | Tejas Research & Development Solution Pvt. Ltd 9918336644 | Suresh Kumar Pandey 7706909311JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134XE | Circle 1 | In Progress |
6
| D/252/AA-2/KDA/16-17 | Circle 1 | CONSTRUCTION OF 940 MINI MIG (G+4) HOUSES AT RAM GANGA ENCLAVE PANKI, KANPUR NAGAR | 0.00 | 10259.74 08/11/2016 | 21/12/2016 20/12/2016 | 19/06/2018 | 21/12/2016 20/12/2016 | Baba Construction 9838225225 | Devendra Chandra Trigunayak 8009556699JE Manoj Kumar Upadhyay 7706909306 AE ASHU MITTAL 9871595959XE | Circle 1 | In Progress |
7
| D/113/AA-1/14-15 | Circle 1 | CONSTRUCTION OF MULTILEVEL PARKING AND TERRACE GARDEN IN PHOOLBAGH | 0.00 | 6656.53 22/04/2014 | 05/06/2014 11/06/2014 | 10/06/2016 | 05/06/2014 11/06/2014 | Suraj Builders 9415127113 | C.B. PANDEY 7060505014 JE AKHILESH SINGH 9457034979 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
8
| D/696/AA-2/KDA/2018-19 | Circle 1 | Development work in front of plot no. E 682 To E 785 of sector-1 of shtabdi Nagar | 0.00 | 88.39 11/09/2018 | 28/11/2018 17/11/2018 | 16/08/2019 | 28/11/2018 17/11/2018 | Ashish Construction | Ram Kumar7235806751JE O.P. Ram7706909316 AE ASHU MITTAL 9871595959XE | Circle 1 | In Progress |
9
| D/504B/AA4/KDA/16-17 | Circle 1 | Construction in drain in Bhagirathi Enclave, Janhavi Enclave part-1 & Janhavi Enclave Part-2 at Village Nagwa. | 0.00 | 1219.22 06/12/2016 | 30/12/2016 23/12/2016 | 22/12/2017 | 30/12/2016 23/12/2016 | G.K.R INFRATECH PVT. LTD 8795999999 | DEVENDRA CHANDRA TRIGUNAYAK 8303170455 JE R K PANDEY 8303170451 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
10
| D/250/AA-1/15-16 | Circle 1 | BEAUTIFICATION & DEVELOPMENT WORK IN GANGA BARRAGE. | 0.00 | 4575.44 18/06/2015 | 06/03/2017 07/09/2015 | 06/03/2017 | 06/03/2017 07/09/2015 | G.R.P Builders 9935626566 | C.B. PANDEY 7060505014 JE S.K. Arora7379173786 AE RANA PRATAP SINGH 7705917134 EX | Circle 1 | In Progress |
11
| .6_D/255/AA-3/16-17 | Circle 1 | ALL DEVELOPMENT WORKS OF KALPI NAGAR AT PANKI BHAU SINGH KANPUR | 0.00 | 2087.99 20/05/2016 | 05/07/2016 02/07/2016 | 01/07/2017 | 05/07/2016 02/07/2016 | Suraj Builders 9415127113 | Indrapal Singh8009551188 JE ANIL KUMAR VERMA 7522002023 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
12
| D/690/AA-1/14-15 | Circle 1 | CONSTRUCTION & DEVELOPMENT WORK AT BOTANICAL GARDEN IN GANGA BARRAGE | 0.00 | 7095.33 11/11/2014 | 28/02/2015 26/02/2015 | 28/08/2016 | 28/02/2015 26/02/2015 | G.R.P Builders 9935626566 | Suresh Kumar Pandey 7706909311 JE S.K. Arora7379173786 AE RANA PRATAP SINGH 7705917134 EX | Circle 1 | In Progress |
13
| D/263/AA-2/KDA/2018-19 | Circle 1 | Construction of 12.50 MLD Capacity Sewage Treatment Plant (Based On Activated Sludge Extended Aeration Technique) including operation & Maintenance for 5 years at Shatabdi Nagar Housing Scheme in Kanpur Nagar (U.P.) | 0.00 | 2172.00 08/02/2018 | 12/04/2018 16/07/2018 | 15/04/2019 | 12/04/2018 16/07/2018 | M/s Enviro Infra Engineers Pvt. Ltd. | Kailash Singh7522882777 JE SHAILENDRA SINGH 9918999906 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
14
| D/88/AA-2/KDA/15-16 | Circle 1 | Construction of RCC Over Head Tank 1250 KL Capacity & 22 m Staging at Shatabdi Nagar Phase-4A Kanpur | 0.00 | 166.83 10/03/2015 | 25/03/2015 01/06/2015 | 31/08/2016 | 25/03/2015 01/06/2015 | S.P. Agarwal & Company 9415039943 | Sanjay Kumar Gupta7706909304 JE Manoj Kumar Upadhyay 7706909306 AE ASHU MITTAL 9871595959 EX | Circle 1 | In Progress |
15
| .4_87/AA4/KDA/17-18 | Circle 1 | construction of 2000.00 K.L. and 22 M staging water storage tank (O.H.T. ) in Bhagirath & Janhvi enclave scheme. | 0.00 | 418.80 06/12/2016 | 30/12/2016 26/05/2017 | 25/05/2018 | 30/12/2016 26/05/2017 | S.P. Agarwal & Company 9415039943 | Devendra Singh8303170098 JE BASANT KUMAR 00 AE D.S.CHAUHAN 9415344541 EX | Circle 1 | In Progress |
16
| D/298/AA4/KDA/13-14 | Circle 1 | Internal Development Work in Highway City Pocket-A, Kanpur. | 0.00 | 926.49 11/10/2013 | 09/12/2013 11/02/2013 | 10/12/2014 | 09/12/2013 11/02/2013 | SINGH ENTERPRISES 9026205526 | Indrapal Singh8009551188JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
17
| 330/AA4/KDA/16-17 | Circle 1 | construction of 30M, 24M,12M,9M,7.50M wide road in Bhagirath Enclave in village Nagwan. | 0.00 | 1217.27 20/07/2016 | 16/09/2016 01/10/2016 | 31/03/2017 | 16/09/2016 01/10/2016 | Suraj Builders 9415127113 | Devendra Singh7388959555JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
18
| D/472/AA-1/15-16 | Circle 1 | INTERNAL DEVELOPMENT WORK FOR DAYANAND VIHAR PHASE-1 | 0.00 | 27.97 06/01/2016 | 26/04/2016 20/02/2016 | 19/05/2016 | 26/04/2016 20/02/2016 | Maa Durga Enterprises 9339101150 | D.K. CHATURVEDI 8707311515JE AJEET KUMAR 7290046145 AE MANOJ KUMAR MISHRA 7897753338XE | Circle 1 | In Progress |
19
| D/299/AA4/KDA/13-14 | Circle 1 | Internal Development of Pocket- B in Highway city ext. part-2 | 0.00 | 644.79 12/11/2013 | 12/12/2013 13/12/2013 | 12/12/2014 | 12/12/2013 13/12/2013 | Avadh Builders 9838529604 | Ravindra Prakash7897239147JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
20
| D/215/56/AA-1/17-18 | Circle 1 | RELOCATION/SHIFTING WORK OF TREES IN GANGA BARRAGE BOTANICAL GARDEN | 0.00 | 38.95 22/06/2017 | 28/08/2017 15/07/2017 | 14/10/2017 | 28/08/2017 15/07/2017 | R.B. Brother & Company 9415052258 | Arun Sharma9919881125JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134XE | Circle 1 | In Progress |
21
| D/393/AA4/KDA/16-17 | Circle 1 | Development of community center in P.A.C. , Kanpur. | 0.00 | 85.63 07/10/2016 | 08/12/2016 04/11/2016 | 03/08/2017 | 08/12/2016 04/11/2016 | | MADAN MOHAN SATI 9918006174JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
22
| 350/AA4/KDA/17-18 | Circle 1 | Development work of remaining road,drains and development of Fadiya Plots at O-Block Kidwai Nagar, kanpur. | 0.00 | 395.94 07/07/2017 | 14/09/2017 10/08/2017 | 09/12/2017 | 14/09/2017 10/08/2017 | KARUNA ENTERPRISES | Indrapal Singh8009551188JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
23
| D/499A/AA4/KDA/16-17 | Circle 1 | water supply work in bhagirathi & janhvi scheme at nagwan village. | 0.00 | 359.09 21/12/2016 | 30/12/2016 23/12/2016 | 22/04/2017 | 30/12/2016 23/12/2016 | Ramesh Kumar 8004938946 | Devendra Singh7388959555 JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541 EX | Circle 1 | In Progress |
24
| D/200/AA4/KDA4/16-17 | Circle 1 | Development work in pocket-F and 24M road in Highway city, Kanpur. | 0.00 | 303.90 28/06/2016 | 22/07/2016 23/07/2016 | 22/01/2017 | 22/07/2016 23/07/2016 | MANORAMA CONSTRUCTION 9415733552 | Ravindra Prakash7897239147JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
25
| D/331/AA4/KDA4/16-17 | Circle 1 | Construction of 30M, 24M, 12M, 9M 7.50M Wide Road in Janhavi Enclave in Village Nagwan. | 0.00 | 1430.10 20/07/2016 | 16/09/2016 15/09/2016 | 14/03/2017 | 16/09/2016 15/09/2016 | Suraj Builders 9415127113 | Ravindra Prakash7897239147JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
26
| D/345/AA4/KDA/16-17 | Circle 1 | Construction of pump house. staff Quatter, laying of raising main & Distribution line in Alaknanda Enclave | 0.00 | 104.73 22/07/2016 | 13/10/2016 01/10/2016 | 30/03/2017 | 13/10/2016 01/10/2016 | Soni Enterprises 7068335491 | Ravindra Prakash7897239147 JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541 EX | Circle 1 | In Progress |
27
| D/365/AA4/KDA/13-14 | Circle 1 | Internal Development of pocket-B in Highway City Ext. part-4 uchati village in Alaknanda Enclave. | 0.00 | 958.44 24/12/2014 | 26/02/2014 26/02/2014 | 25/02/2015 | 26/02/2014 26/02/2014 | SINGH ENTERPRISES 9026205526 | Devendra Singh7388959555JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
28
| D/116/aa4/kda/18-19 | Circle 1 | Construction and Development of 1104(G+4) flats under PMAY at Sakarapur, Kanpur.(Part-1) | 0.00 | 6200.87 26/04/2018 | 10/05/2018 20/07/2018 | 19/01/2020 | 10/05/2018 20/07/2018 | S.S.K.CONSTRUCTION 9415021364 | Sanjay Kumar Gupta7706909304 JE UMESH KUMAR SRIVASTAV 00000000000 AE R K PANDEY 8303170451 EX | Circle 1 | In Progress |
29
| D/504A/AA4/KDA/16-17 | Circle 1 | Laying of Sewer Line in Bhagirathi Enclave, Janhavi Enclave Part-1 & Janhavi Enclave Part-2 at Village Nagwa. | 0.00 | 892.98 07/12/2016 | 30/12/2016 23/12/2016 | 22/06/2017 | 30/12/2016 23/12/2016 | G.K.R INFRATECH PVT. LTD 8795999999 | MADAN MOHAN SATI 7705917145 JE R K PANDEY 8303170451 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
30
| D/1155/AA4/KDA/15-16 | Circle 1 | Development work of Pocket in Dehali Sujanpur of Swarn Jayanti Vistar Part-2 | 0.00 | 489.63 19/09/2015 | 03/11/2015 06/11/2015 | 05/11/2016 | 03/11/2015 06/11/2015 | Kasana Builders Pvt. Ltd 9958797268 | Ravindra Prakash7897239147JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
31
| D/376/AA4/KDA/13-14 | Circle 1 | Internal work in Highway City (Ext.) Part-1. | 0.00 | 157.93 20/09/2014 | 27/11/2014 01/12/2014 | 31/05/2015 | 27/11/2014 01/12/2014 | Divya Enterprises 9839350217 | Ravindra Prakash7897239147JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
32
| 18/AA4/KDA/15-16 | Circle 1 | Construction of 15 MLD Sewage Pumping Station at Highway City Ext. | 0.00 | 344.30 16/03/2015 | 02/11/2015 20/11/2015 | 19/11/2016 | 02/11/2015 20/11/2015 | S.P. Agarwal & Company 9415039943 | Ravindra Prakash7897239147JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
33
| .1_D/32/AA-1/16-17 | Circle 1 | CONSTRUCTION OF 1/2/3 BHK MULTISTORIED RESIDENTIAL APARTMENTS - KDA SIGNATURE GREENS AT VIKAS NAGAR, KANPUR. | 0.00 | 0.00 23/02/2016 | 15/07/2016 | 14/07/2018 | 15/07/2016 | RAMKEE INFRASTRUCTURE LTD. 9999999999 | HASAN RAJA 9415087398 JE AJEET KUMAR 0 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
34
| D/02/AA2/KDA/16-17 | Circle 1 | Construction of 45 m wide road from shatabdi nagar sector-3 to bhauti NH_2 via railway under pass, kanpur | 0.00 | 1239.16 14/03/2016 | 29/04/2016 18/04/2016 | 17/04/2017 | 29/04/2016 18/04/2016 | M/s Hi-Tech Assosiates | 7522882777JE ANIL YADAV 9473618605 AE 9871595959XE | Circle 1 | In Progress |
35
| D/143/AA2/KDA/14-15 | Circle 1 | Construction and Development work of 352 E.W.S. (G+3), 192 L.I.G (G+3) Houses in Pocket–A of Jawahar Puram Vistar Scheme Part-1, 256 E.W.S. (G+3) Houses in Panki Ganga Ganj Phase-1 and 512 E.W.S.(G+3), 368 L.I.G. (G+3) Houses in Shatabdi Nagar Phase-3, for Kanpur Development Authority, Kanpur | 0.00 | 0.00 14/10/2014 | 22/01/2015 | 21/07/2016 | 22/01/2015 | M/s Sunil HiTech Engineers Pvt. Ltd. | RAM KUMAR GUPTA 7235806751 JE UMESH KUMAR SRIVASTAV 00000000000 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
36
| D/53/EE(E/M)/KDA/15-16 | Circle 1 | EXTERNAL ELECTRIFICATION WORK OF 11 KV DOUBLE FEEDER NETWORK AT ALAKNANDA ENCLAVE VILLAGE UCHATI SCHEME, KANPUR. | 0.00 | 92.32 22/04/2015 | 01/06/2015 | 31/12/2015 | 01/06/2015 | | Shishupal Singh7706909307 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
37
| D/38/EE(E/M)/KDA/16-17 | Circle 1 | EXTERNAL ELECTRIFICATION WORK AT SHATABDI NAGAR YOJNA PHASE I & II OF MULTISTORY HOUSES | 0.00 | 365.67 10/03/2016 | 18/05/2016 01/05/2016 | 03/04/2017 | 18/05/2016 01/05/2016 | | Asht Ali Siddiqui9695461245 JE Tejveer Singh9839044423 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
38
| D/177/EE(E/M)/KDA/15-16 | Circle 1 | EXTERNAL ELECTRIFICATION WORK AT L.T. LINE & INSTALLATION OF 400 KVA T/F AT ALAKNANDA ENCLAVE SCHEME | 0.00 | 184.06 05/06/2015 | 28/08/2015 10/09/2015 | 09/06/2016 | 28/08/2015 10/09/2015 | Singh Electronics 9559313131 | Shishupal Singh7706909307 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
39
| D/358/EE(E/M)/KDA/16-17 | Circle 1 | EXTERNAL ELECTRIFICATION & PROVIDING STREET LIGHTING WORK FOR NAVEEN MARKET KANPUR (PART-A&B) | 0.00 | 1105.08 28/09/2016 | 17/11/2016 16/11/2016 | 15/03/2017 | 17/11/2016 16/11/2016 | | Asht Ali Siddiqui9695461245 JE R.R.P. SINGH 9711309013 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
40
| D/433/EE(E/M)/KDA/17-18 | Circle 1 | S/E OF ELECTRICAL METER PANNEL AT SHATABDI NAGAR SULABH AWAS YOJNA TYPE 3 | 0.00 | 143.96 20/09/2017 | 15/01/2018 16/01/2018 | 15/04/2018 | 15/01/2018 16/01/2018 | Asian Switchgear Pvt. Ltd 9839115303 | Asht Ali Siddiqui9695461245 JE Tejveer Singh9839044423 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
41
| D/432/EE(E/M)/17-18 | Circle 1 | S/E OF ELECTRICAL METER PANNEL AT SHATABDI NAGAR SULABH AWAS YOJNA TYPE-2 | 0.00 | 73.59 20/09/2017 | 15/01/2018 16/01/2018 | 15/04/2018 | 15/01/2018 16/01/2018 | Asian Switchgear Pvt. Ltd 9839115303 | Asht Ali Siddiqui9695461245 JE Tejveer Singh9839044423 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
42
| D/39/EE(E/M)/KDA/16-17 | Circle 1 | EXTERNAL ELECTRIFICATION WORK AT SHATABDI NAGAR YOJNA PHASE 4B OF MULTISTORY HOUSES | 0.00 | 437.10 10/03/2016 | 18/05/2016 01/05/2016 | 30/04/2017 | 18/05/2016 01/05/2016 | | Asht Ali Siddiqui9695461245 JE Tejveer Singh9839044423 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
43
| D/74/A.A-3/KDA/18-19 | Circle 1 | 10 SEATED SULABH SHAUCHALAYA COMPLEX WITH SEPTIC TANK AT CATTILE COLONY,KANPUR. | 0.00 | 27.61 27/11/2018 | 22/12/2018 21/02/2019 | 20/08/2019 | 22/12/2018 21/02/2019 | M/S SULABH INTERNATIONAL | Indrapal Singh8449735599 JE ANIL KUMAR VERMA 7522002023 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
44
| D/104/A.A-3/18-19 | Circle 1 | DEVELOPMENT WORK OF OLD MAURANG MANDI AT KANPUR. | 0.00 | 472.81 01/01/2019 | 16/03/2019 02/03/2019 | 01/09/2019 | 16/03/2019 02/03/2019 | Jagdamba Enterprises 9415043332 | SANJAY GAUTAM 9125501558 JE S.K. Arora7379173786 AE ATUL MISHRA 8009837755 EX | Circle 1 | In Progress |
45
| D/13/EE(E/M)/KDA/18-19 | Circle 1 | EXTERNAL ELECTRIFICATION OF 11 KV NETWORK FROM 33 KV S/S SINGHPUR VILLAGE TO KDA GREENS SCHEME, KANPUR | 0.00 | 76.31 09/02/2018 | 04/06/2018 05/04/2018 | 04/07/2018 | 04/06/2018 05/04/2018 | Durgesh Enterprises 9415133227 | Asht Ali Siddiqui9695461245 JE R.R.P. SINGH 9711309013 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
46
| D/597/EE(E/M)/KDA/18-19 | Circle 1 | DISMANTELLING OF 11 KV SINGLE FEEDER EFFECTED MULTISTORY FLATS/PLOTS OF PMAY (KAPLI SCHEME) | 0.00 | 49.50 12/02/2019 | 07/03/2019 08/03/2019 | 07/09/2019 | 07/03/2019 08/03/2019 | Singh Electronics 9559313131 | 7706909307JE R.R.P. SINGH 9711309013 AE 9838611337XE | Circle 1 | In Progress |
47
| D/567/EE(E/M)/KDA/2018-19 | Circle 1 | STREET LIGHTING WORK IN CATTLE COLONY SITUATED AT HAMIRPUR ROAD KANPUR | 0.00 | 6.21 07/01/2019 | 18/02/2019 | 13/03/2019 | 18/02/2019 | SRI MAHAKALESHWAR DEVELOPERS 9956132132 | 9695461245JE VIJAY KUMAR SRIVASTAVA 7706909312 AE 9838611337XE | Circle 1 | In Progress |
48
| D/493/AA-3/KDA/18-19 | Circle 1 | PROVIDING & FIXING RCC FENCING POST 0.10X0.10 X 2.00M SIZE WITH ALL COMPLETE AS PER DIRECTION BY ENG -IN- CHARGE | 0.00 | 100.00 28/12/2018 | 16/03/2019 28/01/2019 | 27/01/2020 | 16/03/2019 28/01/2019 | Bharat Construction & Suppliers 9506040484 | Suresh Kumar Pandey 7706909311 JE Janardhan Ram 7522002012 AE ATUL MISHRA 8009837755 EX | Circle 1 | In Progress |
49
| 13/EE(E/M)/KDA/2018-19 | Circle 1 | NO. 1 (NEAR OHT & MANYAWAR SRI KASHIRAM JI SHAHRI GARIB AWAS YOJNA PART-2 IN HIGHWAY CITY TUBEWELL OHT KANPUR. | 0.00 | 5.22 27/09/2018 | 13/12/2018 29/11/2018 | 28/11/2019 | 13/12/2018 29/11/2018 | | Asht Ali Siddiqui9695461245 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
50
| D/441/EE(E/M)/KDA/2018-19 | Circle 1 | ANNUAL OPERATION & MAINTENANCE OF TUBEWELLS AT HIGHWAYCITY YOJNA TUBEWELL NO. 1 NEAR OHT) & MANYWAR SRI KASHIRAMJI SAHRI GARIB AWAS YOJNA PART-2 IN HIGHWAY CITY TUBEWELL OHT KANPUR. | 0.00 | 5.22 27/09/2018 | 29/11/2018 | 28/11/2019 | 29/11/2018 | | 9695461245JE VIJAY KUMAR SRIVASTAVA 7706909312 AE 9838611337XE | Circle 1 | In Progress |
51
| test | Circle 1 | test work | 0.00 | 15.00 01/02/2019 | 01/02/2019 01/02/2019 | 01/02/2019 | 01/02/2019 01/02/2019 | Aakash Industries 9415125684 | Ram Ashish Sharma ,TEST JE,TEST JE 1 JE AJEET KUMAR,VIJAY SRIVASTAV AE ASHU MITTAL,RANA PRATAP SINGH XE | Circle 1 | In Progress |
52
| D/820/AA2/KDA/18-19 | Circle 1 | Remaining Internal Development work of Sector-14 at jawaharpuram | 0.00 | 150.01 16/10/2018 | 06/03/2019 27/12/2018 | 26/03/2019 | 06/03/2019 27/12/2018 | Nandini Enterprises 9838103757 | Devendra Chandra Trigunayak 8009556699JE Manoj Kumar Upadhyay 7706909306 AE ASHU MITTAL 9871595959XE | Circle 1 | In Progress |
53
| D/963/AA2/KDA/18-19 | Circle 1 | Development work of newly planned plots in Sector-3 at Shatabdi Nagar Scheme | 0.00 | 2334.72 22/01/2019 | 28/02/2019 19/02/2019 | 18/02/2020 | 28/02/2019 19/02/2019 | R & C Infra. Engg. Pvt. Ltd 8052377183 | Kailash Singh7522882777 JE MOHAMMAD QUAMAR 7706909313 AE ASHU MITTAL 9871595959 EX | Circle 1 | In Progress |
54
| D/515/EE(E/M)/KDA/2018-19 | Circle 1 | ANNUAL OPERATION ^& MAINTENANCE OF TUBEWELL NO.1 &2 AT SHATABDI NAGAR HOUSING SCHEME 4B NEAR OHT CAMPUS | 0.00 | 4.19 27/09/2018 | 19/01/2019 | 18/01/2020 | 19/01/2019 | Alokdeep Electricals 9936049777 | BINDU KUMAR SINGH 7706909326 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
55
| D/516/EE(E/M)/KDA/2018-19 | Circle 1 | ANNUAL OPERATION & MAINTENANCE OF TUBEWELL NO. 1, 2 AT SHATABDI NAGAR HOUSING SCHEME PHASE 4A NEAR OHT CAMPUS | 0.00 | 4.19 27/09/2018 | 05/03/2019 19/01/2019 | 18/01/2020 | 05/03/2019 19/01/2019 | Alokdeep Electricals 9936049777 | BINDU KUMAR SINGH 7706909326 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
56
| D/389/AA-1/18-19 | Circle 1 | CONSTRUCTION & DEVELOPMENT WORK OF RAIN WATER HARVESTING THEME PARK AT INDIRA NAGAR IN KANPUR. | 0.00 | 751.46 21/02/2019 | 08/03/2019 | 07/09/2019 | 08/03/2019 | RAMKEE INFRASTRUCTURE LTD. 9999999999 | C.B. PANDEY 7060505014 JE AKHILESH SINGH 9457034979 AE Manoj Kumar Upadhyay 7706909306 EX | Circle 1 | In Progress |
57
| D/589/EE(E/M)/KDA/18-19 | Circle 1 | ANNUAL OPERATION & MAINTENANCE OF TUBEWELL AT MANYAVER SRI KASHIRAMJI SHAHRI GARIB AWAS YOJNAVILLAGE KAPLI PHASE-3 TUBEWELL NO. 1 IN KDA SCHEME KANPUR | 0.00 | 1.76 19/12/2018 | 07/03/2019 15/03/2019 | 14/03/2019 | 07/03/2019 15/03/2019 | SRI MAA SHARDA ENTERPRISE 9335495156 | BINDU KUMAR SINGH 7706909326 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
58
| D/29/AA-1/16-17 | Circle 1 | Widining to road from G.T road kalyanpur to singhpur tiraha. | 0.00 | 1573.42 20/01/2016 | 02/05/2016 21/04/2016 | 20/04/2017 | 02/05/2016 21/04/2016 | Suraj Builders 9415127113 | C.B. PANDEY,HASAN RAJA JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134XE | Circle 1 | In Progress |
59
| D/590/EE(E/M)/KDA/18-19 | Circle 1 | INSTALLING OF LED LIGHTS IN PLACE OF INSTALLED SODIUM LIGHTS AT GAUTAM BUDHHA PARK KANPUR. | 0.00 | 43.45 12/02/2019 | 07/03/2019 08/03/2019 | 07/06/2019 | 07/03/2019 08/03/2019 | Alokdeep Electricals 9936049777 | Ravindra Kumar9794552830JE R.R.P. SINGH 9711309013 AE BASANT LAL 9838611337XE | Circle 1 | In Progress |
60
| D/593/EE(E/M)/KDA/18-19 | Circle 1 | DISMANTALLING OF 33 KV OVER HEAD FEEDERLINES PASSING THROUGH MAHAVEER NAGAR EXTENSIONYOJNA AND RE ERRECTION THROUGH NEW UNDER GROUND 33 KV CABLES | 0.00 | 230.00 06/02/2019 | 11/03/2019 | 10/09/2019 | 11/03/2019 | Singh Electronics 9559313131 | BINDU KUMAR SINGH 7706909326 JE R.R.P. SINGH 9711309013 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
61
| D/493/A.A-3/2018-2019 | Circle 1 | PROVIDING AND FIXING RCC FENCING POST 0.10X0.10X2.00M SIZE WITH ALL COMPLETE AS PER DIRECTION BY ENG-IN-CHARGE. | 0.00 | 100.00 27/12/2018 | 19/03/2019 28/01/2019 | 27/01/2020 | 19/03/2019 28/01/2019 | M/S BHARAT CONSTRUCTION AND SUPPLIERS | Arvind Upaydhyay 7706909315JE ANIL KUMAR VERMA 7522002023 AE Mukesh Agrawal9639004433XE | Circle 1 | In Progress |
62
| D/354/AA-4/KDA/2012-13 | Circle 1 | Earth filling in par-1 pocket-C at Swarn Jayanti Extension Scheme. kanpur | 0.00 | 65.30 30/10/2012 | 10/01/2013 | 04/05/2013 | 10/01/2013 | M/S MANI CONSTRUCTION 9415045029 | MADAN MOHAN SATI 7705917145JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
63
| D/504/AA-4/2017-18 | Circle 1 | CONSTRUCTION OF RCC OHT 1600 KL/22 MTR STAGING & CONS. OF PUMP HOUSE, STAFF QUARTER LAYING OF RISING MAIN & DISTRIBUTION SYSTEM AT SHIVGANGA ENCLAVE CHHATMARA VILLAGE | 0.00 | 182.66 23/05/2017 | 24/05/2018 01/01/2018 | 30/06/2019 | 24/05/2018 01/01/2018 | M/S AWADHESH KUMAR CONTRACTOR 9412049595 | MADAN MOHAN SATI 7705917145JE BASANT KUMAR 9918001512 AE D.S.CHAUHAN 9415344541XE | Circle 1 | In Progress |
64
| D/60/UDYAN/KDA/16-17 | Circle 1 | PLANTATION WORK WITH THREE YEARS MAINTENANCE IN CENTRAL VERGE OF 45 Mtr. ROAD AT SHATABDI NAGAR. | 0.00 | 12.71 25/05/2016 | 08/07/2016 11/07/2016 | 31/07/2019 | 08/07/2016 11/07/2016 | Krishna & Company 933689807 | Pramod Kumar Varma7706909308JE ANIL KUMAR VERMA 7522002023AE Mukesh Agrawal9639004433XE | Circle 1 | In Progress |
65
| D/389/AA-1/KDA/18-19 | Circle 1 | CONSTRUCTION AND DEVELOPMENT WORK OF RAIN WATER HARVESTING THEME PARK AT INDRA NAGAR KANPUR | 0.00 | 751.46 21/02/2019 | 08/03/2019 | 07/09/2019 | 08/03/2019 | RAMKEE INFRASTRUCTURE LTD. 9999999999 | HASAN RAJA 9415087398 JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134 EX | Circle 1 | In Progress |
66
| Testte12 | Circle 1 | Test 12 | 0.00 | 0.00 01/08/2019 | 07/08/2019 06/08/2019 | 01/08/2019 | 07/08/2019 06/08/2019 | Aakash Industries 9415425684 | Anil Kumar7522002023 JE AKHILESH SINGH 9457034979 AE ATUL MISHRA 8009837755 EX | Circle 1 | Not Started |
67
| D/214/Udyan/KDA/13-14 | Circle 1 | Plantation work on road side at vyapar najar area at govind nagar kanpur | 0.00 | 43.80 14/10/2013 | 01/03/2014 | 31/03/2017 | 01/03/2014 | | P. K. GUPTA 7706909320 JE ANIL KUMAR VERMA 7522002023 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
68
| D/301/AA-1/18-19 | Circle 1 | Cleaning of Naveen market compound and maintenance of toilet & clearing sweeping mopping disposal of garbage. | 0.00 | 9.03 04/01/2019 | 01/03/2019 09/01/2019 | 08/04/2019 | 01/03/2019 09/01/2019 | Nandini Enterprises 9838103757 | HASAN RAJA 9415087398 JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134 EX | Circle 1 | Not Started |
69
| D/311/EE(E/M)/KDA/19-20 | Circle 1 | EXTERNAL ELECTRIFICATION WORK OF NEWLY DEVELOPED PLOTS AT MAHAVEER NAGAR EXTENSION SHATABDI NAGAR PHASE 3& 4 etc. | 0.00 | 689.07 13/08/2019 | 09/09/2019 09/09/2019 | 08/05/2020 | 09/09/2019 09/09/2019 | Singh Electronics 9559313131 | BINDU KUMAR SINGH 7706909326 JE R.R.P. SINGH 9711309013 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
70
| D/20/AA-2/KDA/19-20 | Circle 1 | Widening, Strengthening of main roads and Development of Rotaries in Shatabdi Nagar Scheme. | 0.00 | 1593.33 21/06/2019 | 29/09/2019 18/09/2019 | 17/01/2020 | 29/09/2019 18/09/2019 | M/S S R INFRA CONS. PVT. LTD. 9191919191 | Kailash Singh7522882777 JE O.P. Ram7706909316 AE ASHU MITTAL 9871595959 EX | Circle 1 | In Progress |
71
| D/758/AA-2/KDA/18-19 | Circle 1 | Development of reservoir near Ramlala Mandir, Rawatpur Village (Partially) | 0.00 | 303.42 17/11/2018 | 30/09/2019 10/12/2018 | 09/08/2019 | 30/09/2019 10/12/2018 | Deepak Construction 9415157725 | Kailash Singh7522882777 JE MAYANK YADAV 0000000000 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
72
| D/39/EE(E&M)/KDA/2016-17 | Circle 1 | EXTERNAL ELECTRIFICATION WORK AT SHATABDI NAGAR YOJNA PHASE-4 B OF MULTISTORY HOUSES. | 0.00 | 437.10 10/03/2016 | 18/05/2016 01/05/2016 | 30/04/2017 | 18/05/2016 01/05/2016 | DEE CONTROL & ELECTRIC (P) LTD. 9792909090 | BINDU KUMAR SINGH 7706909326 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | Not Started |
73
| D/479A/EE(E&M)/KDA/2019-20 | Circle 1 | SUPPLY HYDROCHLOZIDE AT 87 / WALLS AT SHATABDI NAGAR YOJNA | 0.00 | 0.73 20/11/2019 | 06/02/2020 | 09/02/2020 | 06/02/2020 | RACHNA CONST. Co. 9839162626 | BINDU KUMAR SINGH 7706909326 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | Not Started |
74
| D/26/EE(E/M)/KDA/15-16 | Circle 1 | CONSTRUCTION OF 33/11 K.V. SUB STATION AT NEW TRANSPORT NAGAR PHASE-2 AND 33/11 KV LINE FROM 132 KV S/S DADA NAGAR TO 33/11 KV 5/5 TRANSPORT NAGAR PHASE-2. | 0.00 | 260.35 07/07/2015 | 15/09/2015 07/10/2015 | 06/10/2016 | 15/09/2015 07/10/2015 | Lal chand & Company 9312212493 | Ravindra Kumar9794552830 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE R.R.P SINGH 9711309013 EX | Circle 1 | In Progress |
75
| D/571/AA-1/2019-20 | Circle 1 | CONSTRUCTION WORK OF RCC DIVIDER AT JAJMAU POLICE CHAUKI TO SIDHNATH MANDIR. | 0.00 | 44.66 20/09/2019 | 05/03/2020 29/02/2020 | 28/06/2020 | 05/03/2020 29/02/2020 | Neeraj Trivedi 9415127717 | C.B. PANDEY 7060505014 JE AKHILESH SINGH 9457034979 AE RANA PRATAP SINGH 7705917134 EX | Circle 1 | In Progress |
76
| D/310/AA(E/M)/KDA/2019-20 | Circle 1 | Construction of 2x10 MVA 33/11 K.V. S/s, Substation Building along with Construction of Substation Boundary Wall at Jawaharpuram Sector-8 Housing Scheme, Kanpur. | 0.00 13/06/2019 | 431.52 20/08/2019 | 09/09/2019 09/09/2019 | 08/09/2020 | 09/09/2019 09/09/2019 | Singh Electronics 9559313131 | Ravindra Kumar9794552830 JE NA 0000000000 AE BASANT LAL 0 EX | Circle 1 | In Progress |
77
| D/44/AA(E/M)KDA/2020-21 | Circle 1 | PROVIDING STREET LIGHT WORK FROM SINGHPUR TIRAHA TO RANI LAXMI BAI CHOWK , BITHOOR CUNGI. | 0.00 26/02/2020 | 42.27 26/05/2020 | 09/06/2020 01/06/2020 | 30/09/2020 | 09/06/2020 01/06/2020 | Alokdeep Electricals 9936049777 | Ravindra Kumar9794552830 JE Tejveer Singh9839044423 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
78
| D/85/AA(E/M)KDA/2020-21 | Circle 1 | LT LINE/HT Line/Transformer and construction of New LT/HT Line passing through of plot No.-3 Indra nagar residential Scheme, Kanpur. | 0.00 | 5.31 17/03/2020 | 29/06/2020 08/07/2020 | 07/10/2020 | 29/06/2020 08/07/2020 | Gaurav Construction 9335088825 | Ravindra Kumar9794552830 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
79
| D/559/AA(E/M)/KDA/2019-20 | Circle 1 | Providing Street Lighting Work at Jajmau Police Chauki to Siddanath Temple, Kanpur. | 0.00 | 33.59 17/09/2019 | 07/03/2020 | 06/06/2020 | 07/03/2020 | Singh Electric Co. 9305596292 | Ravindra Kumar9794552830 JE VIJAY KUMAR SRIVASTAVA 7706909312 AE BASANT LAL 9838611337 EX | Circle 1 | In Progress |
80
| D/260/AA-2/KDA/2020-21 | Circle 1 | Provision of Fire Fighting for Affordable Houses(G+4) at Shatabdi Nagar Phase 1 & 2, Jawaharpuram Sector-6 & 13, Ramganga Enclave Yojan | 0.00 | 947.63 20/08/2020 | 08/10/2020 01/10/2020 | 30/09/2021 | 08/10/2020 01/10/2020 | Maya Builders 9838103737 | Arun Sharma9919881125 JE UMESH KUMAR SRIVASTAV 00000000000 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
81
| D/556/AA-1/19-20 | Circle 1 | Remaining work as SPCA Hospital at Raipurwa Kanpur Nagar. | 0.00 | 11.90 05/11/2019 | 18/02/2020 | 17/05/2020 | 18/02/2020 | Tejas Research & Development Solution Pvt. Ltd 9918336644 | C.B. PANDEY 7060505014 JE AKHILESH SINGH 9457034979 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
82
| D/68/AA-2/KDA/2020-21 | Circle 1 | Remaining Development of Shatabdi nagar 3 | 0.00 | 106.76 04/10/2019 | 26/06/2020 03/07/2020 | 02/01/2021 | 26/06/2020 03/07/2020 | R & C Infra. Engg. Pvt. Ltd 8052377183 | Arun Sharma9919881125 JE MOHAMMAD QUAMAR 7706909313 AE ASHU MITTAL 9871595959 EX | Circle 1 | In Progress |
83
| D/106/UDYAN/KDA/2020-21 | Circle 1 | Development Work of Ramleela Park At G-Block Gujaini, Kanpur. | 0.00 | 32.38 29/05/2020 | 21/01/2021 10/09/2020 | 09/01/2021 | 21/01/2021 10/09/2020 | Tejas Research & Development Solution Pvt. Ltd 9918336644 | RAM KUMAR GUPTA 7235806751 JE NO POSTED AE 0000000000 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
84
| D/310/CT/KDA/2020-21 | Circle 1 | Providing & Fixing of Toilet work & Other at Commissioner Camp office. | 0.00 | 6.42 30/12/2020 | 07/01/2021 08/01/2021 | 07/02/2021 | 07/01/2021 08/01/2021 | Jyoti Sales 9839112833 | S.D.TIWARI 83031170044 JE NO POSTED AE 0000000000 AE R.R.P SINGH 9711309013 EX | Circle 1 | In Progress |
85
| D/260/AA-1/20-21 | Circle 1 | Construction of Link road along boundary wall from village to new Airport terminal building, Kanpur (U.P.) | 0.00 | 59.72 22/10/2020 | 08/01/2021 01/01/2021 | 30/04/2021 | 08/01/2021 01/01/2021 | M.P Enterprises 9415052258 | HASAN RAJA 9415087398 JE AKHILESH SINGH 9457034979 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
86
| D/277/AA-1/KDA/20-21 | Circle 1 | Beautification, Road widening, strengthening and installation of tiles in Chandrashekhar Azad Agricultural University Campus. | 0.00 | 27.28 29/05/2020 | 04/11/2020 | 03/03/2021 | 04/11/2020 | Ganpati Enterprises 9935599321 | HASAN RAJA 9415087398 JE AKHILESH SINGH 9457034979 AE Mukesh Agrawal9639004433 EX | Circle 1 | In Progress |
87
| D/293/AA(E/M)/2020-21 | Circle 1 | Providing Street Light work in Community Centre & Park at chakeri. | 0.00 | 24.22 15/10/2020 | 12/02/2021 01/12/2020 | 28/02/2021 | 12/02/2021 01/12/2020 | Shreeganga Electricals 9336933667 | Ravindra Kumar9794552830 JE Tejveer Singh9839044423 AE R.R.P SINGH 9711309013 EX | Circle 1 | In Progress |
88
| D/320/CT/KDA/2020-21 | Circle 1 | Fiber sheet on roof of cycle stand and waterproofing work on roof at KDA Chairman camp. office. | 0.00 | 7.35 11/09/2020 | 11/01/2021 11/01/2021 | 10/02/2021 | 11/01/2021 11/01/2021 | Jyoti Sales 9839112833 | S.D.TIWARI 83031170044 JE NONE 0000000000 AE R.R.P SINGH 9711309013 EX | Circle 1 | In Progress |
89
| test wo5 | Circle 1 | Test4 | 0.00 20/03/2021 | 0.00 | 20/03/2021 20/03/2021 | 08/03/2022 | 20/03/2021 20/03/2021 | A.K Enterprises 9415726829 | AJEET KUMAR YADAV 0 JE AJAY GOEL 0 AE ASHU MITTAL 9871595959 EX | Circle 1 | Not Started |
90
| d/21/udyan/kda/2021-22 | Circle 1 | Plantation Work with 3 Years Maintenance On Both Side Of Road With Iron Tree Guards in Jawaharpuram Yojna Sector-1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12 and 14 (Part-C) Kanpur. | 0.00 10/06/2020 | 32.34 06/02/2021 | 25/06/2021 01/07/2021 | 07/07/2024 | 25/06/2021 01/07/2021 | Kamal Contractor 9918475516 | RAM KUMAR GUPTA 7235806751 JE AMANDEEP TIWARI 000000000 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
91
| D/30/AA-2/KDA/2022-23 | Circle 1 | Construction & Development work of 1152 (G+3) Houses at Shatabdi Nagar Phase-3 & 4 under Pradhanmantri Avas Yojna(Part-2) | 0.00 20/03/2021 | 6783.38 | 21/05/2022 01/05/2022 | 30/10/2024 | 21/05/2022 01/05/2022 | Maa Vaishno Construction Company 9621766282 | Kailash Singh7522882777 JE MAYANK YADAV 0000000000 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
92
| D/35/AA-2/KDA/2021-22 | Circle 1 | Construction of 1536 (G+3) Houses at Jawaharpuram Sector-1 under Pradhanmantri Avas Yojna(Part-4) | 0.00 | 9596.05 | 25/05/2021 | 24/11/2023 | 25/05/2021 | R & C Infra. Engg. Pvt. Ltd 8052377183 | Kailash Singh7522882777 JE SHAILENDRA SINGH 9918999906 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
93
| D/33/AA2/KDA/2022-23 | Circle 1 | Construction of 1536 (G+3) Houses at Jawaharpuram Sector-1 under Pradhanmantri Avas Yojna(Part-5) | 0.00 | 9647.36 | 30/05/2022 26/04/2022 | 25/10/2024 | 30/05/2022 26/04/2022 | R & C Infra. Engg. Pvt. Ltd 8052377183 | Kailash Singh7522882777 JE SHAILENDRA SINGH 9918999906 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
94
| d/265/udyan/kda/2020-21 | Circle 1 | Plantation Work with 3 Years maintenance on Both Side of Road with Iron Tree Guards in Jawaharpuram Yojna Sector- 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12 and 14 (Part-B) | 0.00 16/06/2020 | 33.09 22/10/2020 | 12/04/2021 01/02/2021 | 29/02/2024 | 12/04/2021 01/02/2021 | | RAM KUMAR GUPTA 7235806751 JE NA 0000000000 AE NOT POSTED EX 0000000000 EX | Circle 1 | In Progress |
95
| d/06/AA-4/KDA/2021-22 | Circle 1 | construction of RCC overhead tank 2000kl capacity & 24m stagine at sakarapur housing scheme of KDA, Kanpur. | 0.00 30/01/2021 | 312.13 22/04/2021 | 11/10/2021 01/05/2020 | 31/10/2022 | 11/10/2021 01/05/2020 | S.P. Agarwal & Company 9415039943 | Sanjay Gupta9794552849 JE R K PANDEY 8303170451 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
96
| D/262/EE2/KDA/22-23 | Circle 1 | Internal Development work of Sector-2 at jawaharpuram avas yojna | 0.00 | 3498.19 | 25/10/2022 | 24/04/2024 | 25/10/2022 | R & C Infra. Engg. Pvt. Ltd 8052377183 | Kailash Singh7522882777 JE SHAILENDRA SINGH 9918999906 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
97
| d/244/AA(E/M)/KDA/2022-23 | Circle 1 | Construction of 63 KVA substation for Tubewells at PMAY Scheme Mahaveer Nagar. Shatabdi Nagar Phase-2, 3 & 4 and Jawaharpuram Sector-14 | 0.00 02/06/2022 | 29.11 13/09/2022 | 03/02/2023 15/10/2022 | 14/01/2023 | 03/02/2023 15/10/2022 | SHAKTI ENTERPRISES 8009059111 | Ravindra Kumar9794552830 JE Tejveer Singh9839044423 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
98
| d/203/udyan/kda/2022-23 | Circle 1 | Beautification of Tikonia Park at Jawaharpuram Sector-12 | 0.00 28/07/2022 | 6.24 29/08/2022 | 08/12/2022 01/12/2022 | 30/12/2023 | 08/12/2022 01/12/2022 | | C.B. PANDEY 7060505014 JE NA 0000000000 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
99
| D/399/EE1/KDA/2022-23 | Circle 1 | Remaining work of Community Center at chakeri | 0.00 | 62.42 | 24/12/2023 01/01/2023 | 28/02/2023 | 24/12/2023 01/01/2023 | M/S SHIV SHAKTI TRADERS 0000000000 | C.B. PANDEY 7060505014 JE AMANDEEP TIWARI 000000000 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
100
| D/39/EE4/KDA/2021-22 | Circle 1 | Sakarapur yojna me sarjit315 Bhukhando ka vikas karya | 0.00 | 1758.88 | 24/11/2021 | 23/05/2023 | 24/11/2021 | Jagdamba Enterprises 9415043332 | PRAVIN KUMAR 9918005554 JE UMESH KUMAR SRIVASTAV 00000000000 AE R K PANDEY 8303170451 EX | Circle 1 | In Progress |
101
| D/331/AA-4/KDA/2016-17 | Circle 1 | Construction of 30. mtr. 24.0 mtr. 9.0 mtr. & 7.50 mtr. wide road from Janhvi Yojna at Nagwan | 0.00 | 1430.10 | 01/10/2016 | 31/03/2023 | 01/10/2016 | Suraj Builders 9415127113 | PRAVIN KUMAR 9918005554 JE UMESH KUMAR SRIVASTAV 00000000000 AE R K PANDEY 8303170451 EX | Circle 1 | In Progress |
102
| D/330/AA-4/KDA/2016-17 | Circle 1 | construction of 30M, 24M,12M,9M,7.50M wide road in Bhagirath Enclave in village Nagwan. | 0.00 | 1217.27 | 01/10/2026 | 31/03/2023 | 01/10/2026 | Suraj Builders 9415127113 | PRAVIN KUMAR 9918005554 JE UMESH KUMAR SRIVASTAV 00000000000 AE R K PANDEY 8303170451 EX | Circle 1 | In Progress |
103
| D/444/EE2/KDA/2022-23 | Circle 1 | Development of Rain Harvesting in Shatabdi Nagar yojna(Aman Enclave (G+4), Jawaharpuram Yojna Sector-6(Ekta Enclave(G+4), Jawaharpuram Sector-13 (Pragati Enclave(G+4) and Ram Ganga Enclave Yojna | 0.00 | 107.55 | 02/11/2022 | 01/05/2023 | 02/11/2022 | M/S Singh Construction and Suppliers 000000 | Kailash Singh7522882777 JE MAYANK YADAV 0000000000 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
104
| d/279/EE/KDA/2022-23 | Circle 1 | Construction of 33/11 K.V. Substation (2x10 MVA) at PMAY Mahaveer Nagar Extension Scheeme and 33 K.V. Line from 132 K.V. Substation Jawaharpuram to Proposed 33/11 K.V. S/s Mahaveer Nagar Extenstion & Construction Of Building and Boundary wall. | 0.00 29/07/2022 | 721.38 15/10/2022 | 09/12/2022 16/11/2022 | 15/11/2023 | 09/12/2022 16/11/2022 | Singh Electronics 9559313131 | Kailash Singh7522882777 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
105
| D/595/EE2/KDA/2022-23 | Circle 1 | Repairing of Pots Holes at Sector 4-3, 13-14, 13-08 Jawaharpuram | 0.00 | 9.95 | 21/03/2023 17/03/2023 | 31/03/2023 | 21/03/2023 17/03/2023 | Maya Builders 9838103737 | Arun Sharma9919881125 JE SHAILENDRA SINGH 9918999906 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
106
| D/594/EE2/KDA/2022-23 | Circle 1 | REPAIRING OF POTS AT 2-8 2-3 24 MTR WIDE ROAD AT JAWAHAPURAM | 0.00 | 9.96 | 17/03/2023 | 31/03/2023 | 17/03/2023 | Maya Builders 9838103737 | Arun Sharma9919881125 JE SHAILENDRA SINGH 9918999906 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
107
| d/326(a)/AA/KDA/2022-23 | Circle 1 | External Electrification work in Ganga and Mandakini at Shatabdi Nagar Scheme. | 0.00 30/12/2021 | 166.85 22/12/2022 | 28/02/2023 28/12/2022 | 27/04/2023 | 28/02/2023 28/12/2022 | Singh Electronics 9559313131 | Kailash Singh7522882777 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
108
| D/392/AA(E/M)/KDA/2022-23 | Circle 1 | Construction of 11 Feeder line at jawaharpuram Sector-1 | 0.00 05/11/2022 | 33.01 06/01/2023 | 28/02/2023 28/02/2023 | 27/06/2023 | 28/02/2023 28/02/2023 | Alokdeep Electricals 9936049777 | Kailash Singh7522882777 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
109
| D/409/EE2/KDA/22-23 | Circle 1 | Constructed of Over Head Tank 2200 KL Capacity & 24.0 mtr. Staging, Pump House, Operator Room and Rising Main at Jawaharpuram Avas Yojna Sector-1 under PMAY | 0.00 | 366.96 | 15/03/2023 | 14/09/2024 | 15/03/2023 | S.P. Agarwal & Company 9415039943 | Kailash Singh7522882777 JE MAYANK YADAV 0000000000 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
110
| D/450/EE2/KDA/2022-23 | Circle 1 | Construction work of Gate on NH-2 Mahaveer Nagar Main Road | 0.00 | 85.23 | 17/11/2022 | 06/11/2023 | 17/11/2022 | Subhi Associates 9919959111 | Kailash Singh7522882777 JE SHAILENDRA SINGH 9918999906 AE MANOJ KUMAR UPADHYAY 8303170085 EX | Circle 1 | In Progress |
111
| d/445/S.E.(E/M)/KDA/2022-23 | Circle 1 | Lighting work on the lift side of the statue and on the side of the boundary wall in Gautam Buddha Park. | 0.00 21/12/2022 | 6.89 04/01/2023 | 16/05/2023 06/04/2023 | 05/06/2023 | 16/05/2023 06/04/2023 | SHAKTI ENTERPRISES 8009059111 | Ravindra Kumar9794552830 JE Tejveer Singh9839044423 AE NOT POSTED EX 0000000000 EX | Circle 1 | In Progress |
112
| D/448/AA2/KDA/2022-23 | Circle 1 | Construction of precast temporary boundary on land to be freed from encroachment of authority under Zone 1 and 2 in Kanpur city | 0.00 | 29.92 | 07/11/2022 | 06/11/2023 | 07/11/2022 | Maa Vindhyavasini Construction Company 7985878102 | Kailash Singh7522882777 JE MAYANK YADAV 0000000000 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
113
| D/345/AA2/KDA/2022-23 | Circle 1 | Construction work of boundary wall to protect different types of plots in Shatabdi Nagar Yojna Sector 1 2 3 4 & 5 | 0.00 | 140.44 | 04/01/2023 27/12/2022 | 26/09/2023 | 04/01/2023 27/12/2022 | AKASH ASSOCIATES 00000000 | Kailash Singh7522882777 JE MAYANK YADAV 0000000000 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
114
| d/295/AA(E/M)/kda/22-23 | Circle 1 | Annual Maintenance and operation of Genral Air Conditioning Work at KDA Main Office Building Ground, First, Second and Third Floor and Auditorium., | 0.00 25/09/2022 | 23.36 01/09/2021 | 25/02/2023 01/09/2021 | 30/06/2022 | 25/02/2023 01/09/2021 | LG ELECTRONICS INDIA PVT.LTD. 9918732225 | Ravindra Kumar9794552830 JE Tejveer Singh9839044423 AE NA 00000000000 EX | Circle 1 | In Progress |
115
| D/247/EE2/KDA/2022-23 | Circle 1 | DEVELOPMENT & RENOVATION WORK OF MAMA TALAB | 0.00 | 487.08 | 10/10/2022 | 09/10/2023 | 10/10/2022 | M/S GOMDHARI 000000000 | Kailash Singh7522882777 JE SHAILENDRA SINGH 9918999906 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
116
| D/90/S.E./KDA/2023-24 | Circle 1 | External Electrification work in W Block B M Markey, Juhi, Kanpur Nagar. | 0.00 14/07/2022 | 29.87 20/03/2023 | 16/06/2023 03/06/2023 | 02/09/2023 | 16/06/2023 03/06/2023 | ANURAG CONST.CO. 9450347794 | Ravindra Kumar9794552830 JE Tejveer Singh9839044423 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
117
| D/364/AA/KDA/2022-23 | Circle 1 | Lighting on the divider of the road from shatabdi Dwar to Cambrij School as well as the work of lighting on 45m and 24m road of Bhagirathi Janhavi Yojna | 0.00 19/11/2022 | 128.27 28/12/2022 | 19/05/2023 06/02/2023 | 05/08/2023 | 19/05/2023 06/02/2023 | | PRAVIN KUMAR 9918005554 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
118
| D/354/AA(E/M)/KDA/2020-21 | Circle 1 | Providing 11 K.V. Line from Shatabdi Nagar 11 K.V. Double Feeder line to KDA Dreams Substation. | 0.00 02/03/2020 | 9.26 22/10/2020 | 26/03/2021 27/01/2021 | 26/03/2021 | 26/03/2021 27/01/2021 | SRI MAA SHARDA ENTERPRISE 9335495156 | Ravindra Kumar9794552830 JE NA 0000000000 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
119
| D/589/AA(E/M)/KDA/18-19 | Circle 1 | Annual Operation & Maintenance of Tubewell at Manyavar Sri Kashi ram ji Shahri garib awas Yojna Village Kapli Phase-3 tubewell no-1 in KDA Scheme, Kanpur. | 0.00 24/10/2018 | 1.76 21/12/2018 | 07/03/2019 15/03/2019 | 14/03/2020 | 07/03/2019 15/03/2019 | SRI MAA SHARDA ENTERPRISE 9335495156 | Ravindra Kumar9794552830 JE Tejveer Singh9839044423 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
120
| D/89/S.E.(E/M)/KDA/2023-24 | Circle 1 | External electrification and lighting work in the remaining part of Bingawan Morang Mandi. | 0.00 14/12/2022 | 23.00 20/03/2023 | 02/08/2023 03/06/2023 | 02/09/2023 | 02/08/2023 03/06/2023 | | Ravindra Kumar9794552830 JE Tejveer Singh9839044423 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
121
| d/22/udyan/kda/2023-24 | Circle 1 | Beautification of Ahilyabai Park In front of Block 68 at Dabauli ward-72 Kanpur. | 0.00 22/12/2022 | 10.38 06/01/2023 | 07/06/2023 16/05/2023 | 15/01/2024 | 07/06/2023 16/05/2023 | Kamal Contractor 9918475516 | NA 0000000000 JE MAYANK YADAV 0000000000 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
122
| d/363/AA/KDA/2022-23 | Circle 1 | Lighting operation and mentinance of lighting system Kalyanpur to singhpur tirha, Singhpur tiraha to DPS School Azad Nagar (Mainavati Marg), Botanical garden Ganga Bairaj to Yash Hospital(Kothari Chaura). Yash Hospital Kothari Square to Mandhana Mod ands GT Road From Mandhana Tiraha to Bithoor entrance to Chungi Square. | 0.00 03/10/2022 | 699.08 28/12/2022 | 06/04/2023 06/02/2023 | 05/08/2023 | 06/04/2023 06/02/2023 | | Ravindra Kumar9794552830 JE AMANDEEP TIWARI 000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
123
| d/19/udyan/kda/2023-24 | Circle 1 | Beautification of Park Situated at In Front of Building No. 58B/10, 11, 12 at Dabauli-2 Kanpur. | 0.00 21/12/2022 | 8.21 06/01/2023 | 13/06/2023 16/05/2023 | 15/07/2024 | 13/06/2023 16/05/2023 | Singh Traders 9838878338 | Suresh Kumar Pandey 7706909311 JE MAYANK YADAV 0000000000 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
124
| d/444/AA(E/M)/KDA/2022-23 | Circle 1 | Annual Operation of installed Electric Accessories & fountains at Chaudhari Harmohan Singh Ekta Park. | 0.00 22/12/2022 | 2.37 04/01/2023 | 19/05/2023 06/04/2023 | 05/03/2024 | 19/05/2023 06/04/2023 | | Ravindra Kumar9794552830 JE NA 0000000000 AE EXECUTIVE ENGINEER 00000000 EX | Circle 1 | In Progress |
125
| D/262/S.E.(E/M)/KDA/2022-23 | Circle 1 | S/E of Electrcal Meter Panel Shatabdi Nagar Phase-2&3 (Type-2&3) in Yamuna, Mandakimi and Ganga Block, Kanpur. | 0.00 01/06/2022 | 116.45 15/10/2022 | 09/12/2022 01/11/2022 | 28/02/2023 | 09/12/2022 01/11/2022 | Singh Electronics 9559313131 | Kailash Singh7522882777 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
126
| D/40/AA-4/K.D.A/2023-24 | Circle 1 | Barbed wire fencing & Construction of Precast temporary Boundary wall on Land Freed From Illegal in Engineering Zone-4 | 0.00 11/04/2022 | 50.00 22/02/2023 | 25/05/2023 16/05/2023 | 15/10/2023 | 25/05/2023 16/05/2023 | | PRAVIN KUMAR 9918005554 JE NA 0000000000 AE R K PANDEY 8303170451 EX | Circle 1 | In Progress |
127
| D/23/UDYAN/KDA/2023-24 | Circle 1 | Beautification of Park Near Block-56 at Dabauli Ward-72 Kanpur. | 0.00 21/12/2022 | 9.28 06/01/2023 | 07/06/2023 16/05/2023 | 15/01/2024 | 07/06/2023 16/05/2023 | Kamal Contractor 9918475516 | Suresh Kumar Pandey 7706909311 JE MAYANK YADAV 0000000000 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
128
| D/329/AA(E/M)/KDA/2023-24 | Circle 1 | External Electrification work in New Developed plots at Jawaharpuram Sector-14 | 0.00 19/04/2023 | 80.11 11/08/2023 | 30/10/2023 11/10/2023 | 10/02/2024 | 30/10/2023 11/10/2023 | Alokdeep Electricals 9936049777 | Ravindra Kumar9794552830 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
129
| D/76/AA2/KDA/2023-24 | Circle 1 | Strengthning of Internal & External Road, Drain, Construction of Park at Kalindri Nagar Kanpur | 0.00 | 260.60 | 06/07/2023 20/06/2023 | 19/03/2024 | 06/07/2023 20/06/2023 | Rajat Construction 9559313131 | Kailash Singh7522882777 JE SHUDHANSU SRIVASTAVA 8172879575 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
130
| D/583/AA2/KDA/2022-23 | Circle 1 | Construction of two lane road parallel to Lower Ganga Canal from Panki Kalyanpur Marg to New Shivali Road | 0.00 | 3503.95 | 24/03/2023 15/03/2023 | 14/03/2024 | 24/03/2023 15/03/2023 | R.R. Enterprises 9793923473 | Kailash Singh7522882777 JE SHAILENDRA SINGH 9918999906 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
131
| D/274/udyan/KDA/2020-21 | Circle 1 | Plantation work with 3 Years Maintenance around the Residential Campus and Both Side of Road with Iron Tree Guards in Shatabdi Nagar, Phase-3 Kanpur. | 0.00 28/06/2020 | 32.04 31/07/2020 | 19/03/2021 01/02/2023 | 29/02/2024 | 19/03/2021 01/02/2023 | Neetu Enterprises 9936614752 | C.B. PANDEY 7060505014 JE NA 0000000000 AE DHIRENDRA BAJPAI 00000000000 EX | Circle 1 | In Progress |
132
| D/223/AA/KDA/2023-24 | Circle 1 | Operation and Maintenance of Tubewells for water supply in diffrent scheme of KDA. | 0.00 11/04/2022 | 37.36 13/06/2023 | 11/11/2023 24/07/2023 | 23/07/2024 | 11/11/2023 24/07/2023 | | PRAVIN KUMAR 9918005554 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
133
| D/48/EE2/KDA/2023-24 | Circle 1 | Constructed of 3 nos. and shop, general store, milk booth, stair case and toilet at two places between 5040(G+3)Houses under Mahavir Nagar Yojna | 0.00 | 81.96 | 08/05/2023 01/05/2023 | 31/01/2024 | 08/05/2023 01/05/2023 | M/S SHIV SHAKTI TRADERS 0000000000 | Kailash Singh7522882777 JE SHAILENDRA SINGH 9918999906 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
134
| D/92/AA/KDA/2023-24 | Circle 1 | Providing Street Light work at highway City Scheeme Kanpur. | 0.00 21/12/2022 | 111.36 13/03/2023 | 15/06/2023 03/06/2023 | 02/12/2023 | 15/06/2023 03/06/2023 | Prashant Enterprises 9415041977 | PRAVIN KUMAR 9918005554 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
135
| D/153/udyan/KDA/2023-24 | Circle 1 | Beautification of Park Between Telephone Exchange Colony and Ganesh Shanker Vidyarthi Nagar. | 0.00 27/01/2023 | 64.08 26/09/2023 | 05/12/2023 16/11/2023 | 15/11/2024 | 05/12/2023 16/11/2023 | | C.B. PANDEY 7060505014 JE NA 0000000000 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
136
| D/493/AA/KDA/2023-24 | Circle 1 | Lighting Work on the main road of Jawahar Puram Sector-1. | 0.00 01/11/2023 | 31.39 03/01/2024 | 14/03/2024 22/01/2024 | 21/05/2024 | 14/03/2024 22/01/2024 | Alokdeep Electricals 9936049777 | Kailash Singh7522882777 JE NA 0000000000 AE NA 00000000000 EX | Circle 1 | In Progress |
137
| D/459/EE2/KDA/23-24 | Circle 1 | Cleaning of sewer line at shatabdi nagar sector-4 | 0.00 | 7.42 | 04/01/2024 05/12/2023 | 04/06/2024 | 04/01/2024 05/12/2023 | M/S SAVITRI BUILDERS 9454751619 | Kailash Singh7522882777 JE MAYANK YADAV 0000000000 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |
138
| D/283/EE2/KDA/2023-24 | Circle 1 | cleaning of sewer line & repair of manhole at kalindri nagar | 0.00 | 7.87 | 04/03/2024 01/02/2024 | 31/07/2024 | 04/03/2024 01/02/2024 | M/S KUSUMAA ENTERPRISES 8795860050 | Kailash Singh7522882777 JE SHUDHANSU SRIVASTAVA 8172879575 AE AJAY PANWAR 9918001620 EX | Circle 1 | In Progress |